This is not a replacement for the official study guide. Please read the official study guide first — use this exam prep only to reinforce or practice your understanding.
Free CISA exam practice questions with answers and explanations, organized by domain and part.
Domain 2: Governance and Management of IT
Q1 Ernie, a CIO overseeing a large IT department, wants to draft a mission statement for his team. What is the BEST starting point for this effort?
- A. The findings of the most recent risk assessment
- B. The backlog of open items in the project portfolio
- C. The organization's own mission statement
- D. Ernie's most recent performance appraisal
Answer: C
IT departments function best when their direction is aligned with the business they serve. The soundest starting point for an IT mission statement is therefore the organization's overall mission statement, since this keeps the department's purpose tied to enterprise goals. If no such statement exists, the CIO can instead draw on his own understanding of the organization's purpose to craft one that still supports it. A risk assessment, a performance appraisal, and the project backlog are all narrower, operational inputs that don't capture the organization's broader purpose.
Domain 3: IT Life Cycle Management
Q2 A program manager, after reviewing the outcomes of past large projects, decides to introduce a gate process for future ones. What requirement will this process MOST likely add to subsequent projects?
- A. Approval must be obtained before a project may begin.
- B. Approval must be obtained before a project is considered complete.
- C. Approval must be obtained for any requirement that was not met.
- D. Approval must be obtained before a project can move into its next phase.
Answer: D
A gate-process approach to the SDLC requires a formal review at the end of each phase, and only once management is satisfied that the phase's objectives and requirements have been met is the project permitted to advance to the next phase. The review typically takes the form of a meeting in which project status is presented to decision-makers. The other options describe approvals tied to project start, project completion, or unmet requirements, none of which reflect the phase-by-phase gating this process introduces.
Domain 4: IT Service Management and Continuity
Q3 While reviewing an organization's risk management documentation, an IS auditor notices a statement of impact included in the audit materials. What is the PRIMARY purpose of including such a statement in an impact analysis?
- A. To highlight threats that carry no operational impact
- B. To present business impact in terms stakeholders can relate to
- C. To guarantee that every possible impact has been addressed
- D. To summarize the outcomes of the risk analysis
Answer: B
A statement of impact exists to translate risk findings into terms that are meaningful to the business, helping stakeholders grasp the real-world consequences of various risks and supporting better prioritization and decision-making. Merely summarizing risk-analysis results would leave those findings uncontextualized. Listing threats with no impact would add irrelevant clutter rather than aid communication. And while comprehensive risk coverage is a broader goal of risk management, it is not what the impact statement itself is meant to achieve - its role is communication, not completeness.
Domain 4: IT Service Management and Continuity
Q4 To satisfy the BIA goal of compiling a complete list of all identifiable business processes and systems, which technique is MOST commonly used to gather that information?
- A. Criticality analysis
- B. Documentation review
- C. Questionnaire or intake form
- D. Network diagram review
Answer: C
A questionnaire or intake form is the tool typically used to gather the data needed to identify all processes and systems, since it can be distributed broadly and captures information directly from process owners. Network diagram review is unlikely to surface every business process, and documentation review often falls short too, especially in less mature organizations where processes aren't fully documented. Criticality analysis, meanwhile, operates on processes that have already been identified through other means, so it comes too late to serve this particular purpose.
Domain 3: IT Life Cycle Management
Q5 Change management and configuration management are MOST closely associated with which phase of the SDLC?
- A. Testing
- B. Requirement definition
- C. Maintenance
- D. Design
Answer: C
Change management and configuration management are the core operational disciplines that keep systems stable and controlled during the maintenance phase of the SDLC, long after initial development and testing have concluded.
Domain 3: IT Life Cycle Management
Q6 Which type of testing BEST confirms that each individual software module performs correctly on its own?
- A. System
- B. Penetration
- C. Integration
- D. Unit
Answer: D
Unit testing verifies that individual modules - such as a single function or method - work correctly in isolation, before they are combined with other parts of the application. Integration testing instead checks how combined modules interact, while system testing validates the application end-to-end as a whole. Penetration testing has a different purpose altogether: it probes for exploitable security weaknesses rather than confirming functional correctness. Of these, only unit testing targets the correctness of individual modules.
Domain 3: IT Life Cycle Management
Q7 What is the primary purpose behind an organization adopting a "gate process" within its systems development life cycle (SDLC)?
- A. To evaluate how much budget has been spent at each stage
- B. To eliminate the need for reviewing the project
- C. To resolve problems that arise during each phase
- D. To require review and sign-off on each phase before moving forward
Answer: D
The core intent of a gate process is to require formal review and approval of each phase before the project is allowed to proceed, which preserves project integrity and keeps the work aligned with organizational objectives. This is the opposite of eliminating reviews, since the process is built entirely around periodic checkpoints. Resolving in-phase problems is a broader project-management concern that isn't specific to gating, and tracking budget consumption, while sometimes part of a gate review, is not the main reason the process exists - the emphasis is on verifying readiness to proceed, not on cost tracking alone.
Domain 3: IT Life Cycle Management
Q8 Which of the following is NOT typically a responsibility of a project manager?
- A. Tracking project costs
- B. Approving changes to the project
- C. Building the project schedule
- D. Communicating project status
Answer: B
Project managers generally do not hold the authority to approve changes affecting scope, cost, or resources themselves; that authority usually rests with a change control board or sponsor, while the project manager's role is to build the schedule, track costs, and report status.
Domain 4: IT Service Management and Continuity
Q9 What is the MOST important reason for an IS auditor to recommend that an organization define the maximum tolerable downtime (MTD) for each critical process?
- A. To help coordinate recovery activities
- B. To set the ceiling for acceptable data loss
- C. To support the organization's survival through a disaster
- D. To define the maximum level of risk the organization will tolerate
Answer: C
Defining the MTD for critical processes matters most because it supports the organization's ability to survive a disaster: knowing the MTD lets the organization prioritize which processes to restore first and allocate recovery resources so that critical operations resume before the damage becomes irreversible. Acceptable data loss is instead governed by recovery point objectives, not MTD, and an overarching risk tolerance is a separate, broader risk-management concept. While MTD does feed into coordinating recovery efforts, its deeper purpose is preventing organizational failure, not coordination for its own sake.
Domain 5: Information Asset Protection
Q10 Under US law, what must an organization do upon discovering child pornography on an employee's workstation?
- A. Notify law enforcement only once the workstation is decommissioned.
- B. Notify law enforcement right away.
- C. Notify law enforcement only after the employee has been terminated.
- D. Notify law enforcement only after the employee admits to viewing it.
Answer: B
US organizations are legally required to notify law enforcement immediately upon discovering child pornography on any computer or workstation - there is no requirement to wait for a confession, termination, or decommissioning first.