Domain 3: IT Life Cycle Management

Q421 The BEST source of requirements for an RFP project is:

Answer: D

An organization developing an RFP (request for proposals) for vendor products or services needs to develop these requirements internally.

Domain 1: Information System Auditing Process

Q422 For audit planning purposes, may an auditor rely on the audit client's own risk assessment?

Answer: D

An auditor can rely on a risk assessment performed by a qualified external party to build a risk-based audit plan, with higher-risk areas examined more closely than lower-risk ones.

Domain 2: Governance and Management of IT

Q423 An organization wants to hire an executive to build a management program addressing threats and vulnerabilities. What's the BEST job title for this role?

Answer: D

The CRO (chief risk officer) manages risk across multiple asset types, commonly information assets as well as physical assets and/or workplace safety. In financial services organizations, the CRO also manages risks tied to financial transactions or asset portfolios.

Domain 5: Information Asset Protection

Q424 What technique does PGP use to let multiple users read an encrypted document?

Answer: D

PGP uses a digital envelope to encapsulate multiple public keys, permitting multiple users to read an encrypted document.

Domain 3: IT Life Cycle Management

Q425 Which is a critical element during the requirements definition phase of the SDLC?

Answer: D

User involvement is critical during requirements definition, ensuring the system aligns with users' actual needs. Direct user participation leads to a more accurate, comprehensive understanding of necessary functions and features, supporting a more successful implementation. Management commitment, though important for project support, doesn't specifically ensure accurate requirements. Skilled developers build quality systems but their expertise alone doesn't guarantee requirements are met without proper user input. Adequate funds matter for project completion but don't affect requirement accuracy or completeness—without user input, even a well-funded project with skilled developers may miss its objectives.

Domain 4: IT Service Management and Continuity

Q426 A new IT manager is improving the organization's efforts to make systems and devices more resilient to attack. What should the manager update?

Answer: D

A system and device hardening standard specifies the configurations needed to make systems and devices more resistant to attack.

Domain 3: IT Life Cycle Management

Q427 While reviewing a multiquarter project's status and schedule, the project manager realizes it will likely finish at least a month late. Assuming no particular notification requirements exist, when should the project manager inform the project sponsor?

Answer: D

Absent specific stipulations about reporting exceptions and risks, a project manager should immediately inform the project sponsor of a delay of this magnitude.

Domain 3: IT Life Cycle Management

Q428 Which of the following is a formal verification of system specifications and technologies?

Answer: D

Quality assurance testing formally verifies system specifications and technologies. Users typically aren't involved in QAT; it's usually performed by IT or IS departments instead.

Domain 3: IT Life Cycle Management

Q429 What is the PRIMARY business purpose of a configuration management database?

Answer: A

In business terms, a configuration management database (CMDB) records all configuration changes made to IT systems. "Providing information about configurations" only partly captures a CMDB's purpose. "Recording approvals for changes" is incorrect since approval records belong in a change management business record. "Recording only the most recent change" is incorrect since configuration management concerns all changes, not just the latest ones.

Domain 3: IT Life Cycle Management

Q430 An organization issues an RFP to replace a large business application, evaluates and scores responses, and arrives at three finalists. What should the organization do NEXT?

Answer: D

For a significant RFP project, it's often wise to begin negotiations with more than one finalist. Negotiations sometimes stall; starting with only a single vendor risks wasting more time if that negotiation fails than if two or three are begun in parallel.